Heyday5 Pty Ltd v Cockram Constructions NSW Pty Ltd [2015] NSWSC 884

Heyday5 Pty Ltd v Cockram Constructions NSW Pty Ltd [2015] NSWSC 884

The plaintiff had a strong prima facie case and there was a serious question to be tried about whether Practical Completion had occurred and whether, on the proper construction of the Contract, the defendants were obliged to release the Bond. Although the balance of convenience was finely balanced and there was limited evidence of reputational or financial harm, the injunctions would preserve the practical status quo, the defendants had not shown particular prejudice, and the balance of convenience overall favoured interlocutory relief.

Jurisdiction
Australia
Judgment Date
02 July 2015
Procedural Posture
Application for Interlocutory Injunction Concerning a Performance Bond Under a Construction Sub Contract / Interlocutory Application Pending Final Determination of the Proceedings
Outcome
Interlocutory injunction granted
Legal Topics
['interlocutory Injunction' 'performance Bond' 'security for Performance' 'practical Completion' 'serious Question to Be Tried' 'balance of Convenience']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Application for Interlocutory Injunction Concerning a Performance Bond Under a Construction Sub Contract / Interlocutory Application Pending Final Determination of the Proceedings

  1. 1 ["Whether there was a serious question to be tried that, once Practical Completion was achieved, the plaintiff's obligations under the Bond were released and the defendants were obliged to return the Bond." 'Whether any obligation to release the Bond was subject to any pre-existing or accrued right of the defendants under clause 28(c) of the Standard Conditions.' 'Whether Practical Completion had occurred as a matter of fact.' 'Whether the balance of convenience favoured restraining the first and second defendants from demanding payment under the Bond and restraining QBE from paying under the Bond.']

Ratio Decidendi

The plaintiff had a strong prima facie case and there was a serious question to be tried about whether Practical Completion had occurred and whether, on the proper construction of the Contract, the defendants were obliged to release the Bond. Although the balance of convenience was finely balanced and there was limited evidence of reputational or financial harm, the injunctions would preserve the practical status quo, the defendants had not shown particular prejudice, and the balance of convenience overall favoured interlocutory relief.

Court Disposition

Interlocutory injunction granted

Orders

  • ['Until further order the first and second defendants be restrained from making any demand for payment under the Bond.' 'Until further order the third defendant be restrained from making payment pursuant to the Bond.' "The costs of this application be the plaintiff's costs in the cause." 'No order as to the costs of...