Frangieh & anor v Inner West Council [2016] NSWLEC 1472
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with the agreed orders approving the development application subject to conditions.
- Jurisdiction
- Australia
- Judgment Date
- 13 September 2016
- Procedural Posture
- Class 1 Development Application Appeal / Final Orders Following Conciliation Conference and Agreement Under S 34(3) of the Land and Environment Court Act 1979
- Outcome
- Appeal upheld; Development Application D/2016/126 approved subject to conditions.
- Legal Topics
- ['development Application' 'conciliation Conference' 'agreement Between Parties' 'clause 4.6 Variation' 'costs Under S 97 B of the Environmental Planning and Assessment Act 1979']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 1 Development Application Appeal / Final Orders Following Conciliation Conference and Agreement Under S 34(3) of the Land and Environment Court Act 1979
Legal Issues
- 1 ["Whether the parties' agreement under s 34(3) of the Land and Environment Court Act 1979 could be given effect by orders of the Court." "Whether Development Application D/2016/126 should be approved subject to conditions pursuant to the parties' agreement."]
Ratio Decidendi
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with the agreed orders approving the development application subject to conditions.
Court Disposition
Appeal upheld; Development Application D/2016/126 approved subject to conditions.
Orders
- ["The Applicant is granted leave to rely upon the amended plans and documentation as referred to in Condition 1 of Annexure 'A' annexed hereto;" 'The cl 4.6 variation to cl 4.4(2) of Leichhardt Environmental Plan 2013 prepared by Think Planners Pty Ltd is agreed by the parties to be well founded and is upheld;' 'The...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment