Interco Pty Ltd v Schiavello Systems (NSW) Pty Ltd [2006] NSWSC 58

Interco Pty Ltd v Schiavello Systems (NSW) Pty Ltd [2006] NSWSC 58

There is no genuine dispute as to the proper debtor; analysis of the facts most favourable to the plaintiff still establishes Interco Pty Limited as the contracting party, so the statutory demand stands.

Jurisdiction
Australia
Judgment Date
01 February 2006
Procedural Posture
Application to Set Aside Statutory Demand / Judgment After Hearing
Outcome
Application to set aside statutory demand dismissed. Time for compliance with the statutory demand extended to 22 February 2006.
Legal Topics
['statutory Demand' 'genuine Dispute' 'company Groups' 'provisional Contract' 'authority to Contract']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Application to Set Aside Statutory Demand / Judgment After Hearing

  1. 1 ['Whether there exists a genuine dispute about the indebtedness between the parties under s 459G of the Corporations Act 2001 (Cth)' 'Identification of the correct contractual party within a group of companies' 'Effect and formation of a provisional contract and subsequent formal contract']

Ratio Decidendi

There is no genuine dispute as to the proper debtor; analysis of the facts most favourable to the plaintiff still establishes Interco Pty Limited as the contracting party, so the statutory demand stands.

Court Disposition

Application to set aside statutory demand dismissed. Time for compliance with the statutory demand extended to 22 February 2006.

Orders

  • ['Application dismissed' 'Costs awarded against the applicant' 'Time for compliance with statutory demand extended to 22 February 2006']