Howe v NSW Coastal Homes Pty Ltd [2016] NSWCATAP 127
Leave to appeal was granted for both appeals because the Tribunal erred by not including establishment and insurance costs and GST as substantiated in evidence, and to a limited extent in procedural fairness regarding submissions on the form of order. However, the substantive monetary order was confirmed, not replaced by a rectification order, and the builder was ordered to pay the remaining amount reflecting establishment/insurance and GST.
- Jurisdiction
- Australia
- Judgment Date
- 16 June 2016
- Procedural Posture
- Internal Appeal (home Building Dispute) / Appeal Panel Determination After Leave Granted on Both Appeal and Cross Appeal
- Outcome
- Leave to appeal granted for both main appeal and cross-appeal; builder's appeal dismissed; cross-appeal upheld on quantum; payment orders confirmed and varied.
- Legal Topics
- ['internal Appeals' 'procedural Fairness' 'rectification Orders' 'statutory Interpretation' 'home Building Statutory Warranties' 'remedies in Building Disputes']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Internal Appeal (home Building Dispute) / Appeal Panel Determination After Leave Granted on Both Appeal and Cross Appeal
Legal Issues
- 1 ['Whether leave to appeal should be granted for both appeal and cross-appeal' 'Whether the Tribunal erred by not making a rectification order instead of a monetary order' 'Whether exclusion of establishment/insurance costs and failure to account for GST constituted error' 'Whether there was a denial of procedural fairness in not hearing further submissions on the nature of the orders']
Ratio Decidendi
Leave to appeal was granted for both appeals because the Tribunal erred by not including establishment and insurance costs and GST as substantiated in evidence, and to a limited extent in procedural fairness regarding submissions on the form of order. However, the substantive monetary order was confirmed, not replaced by a rectification order, and the builder was ordered to pay the remaining amount reflecting establishment/insurance and GST.
Court Disposition
Leave to appeal granted for both main appeal and cross-appeal; builder's appeal dismissed; cross-appeal upheld on quantum; payment orders confirmed and varied.
Orders
- ['AP 15/65418: Leave to appeal granted; appeal dismissed.' 'AP 15/66881: Leave to appeal granted; order for payment of $41,700 by NSW Coastal Homes Pty Ltd to AJ Howe and JM Howe confirmed; NSW Coastal Homes Pty Ltd to pay AJ Howe and JM Howe an additional sum of $11,794.11 within 28 days.' 'No order as to costs.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment