Iris Property Group v Hunters Hill Council [2015] NSWLEC 1203

Iris Property Group v Hunters Hill Council [2015] NSWLEC 1203

Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were required to be disposed of in accordance with that decision and written orders were made to give effect to it.

Jurisdiction
Australia
Judgment Date
05 June 2015
Procedural Posture
Modification Application / Class 1 Conciliation Conference; Agreement Under S 34(3) of the Land and Environment Court Act 1979
Outcome
Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979.
Legal Topics
['modification Application' 'conciliation Conference' 'agreement Between the Parties' 'section 34 Orders']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Modification Application / Class 1 Conciliation Conference; Agreement Under S 34(3) of the Land and Environment Court Act 1979

  1. 1 ['Whether the parties had reached an agreement under s 34(3) of the Land and Environment Court Act 1979 as to terms of a decision acceptable to them.' 'Whether the agreed decision was one that the Court could have made in the proper exercise of its functions.']

Ratio Decidendi

Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were required to be disposed of in accordance with that decision and written orders were made to give effect to it.

Court Disposition

Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979.

Orders

  • ["Final orders to give effect to the parties' agreement were made on 5 June 2015."]