J C Butko Engineering Pty Ltd v Talis Civil Pty Ltd (No 2) [2021] NSWDC 823
The defendant's application was refused because the plaintiff had obtained a final judgment on Payment Claim 13, succeeded on the strike out aspects of the motion, and faced withdrawn or failed challenges by the defendant; the plaintiff's substantial success justified a favourable costs order despite the defendant preserving its defence to Payment Claim 14.
- Jurisdiction
- Australia
- Judgment Date
- 10 December 2021
- Procedural Posture
- Civil Procedural Ruling on Costs / Defendant's Application to Vacate and Vary a Costs Order Made After Summary Judgment and Strike Out Orders
- Outcome
- Defendant's application refused; orders made on 29 October 2021 confirmed; defendant ordered to pay the costs of the application to vacate and vary the costs order.
- Legal Topics
- ['summary Judgment' 'strike Out of Defence' 'costs Follow the Event' 'partial Success' 'costs Discretion']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil Procedural Ruling on Costs / Defendant's Application to Vacate and Vary a Costs Order Made After Summary Judgment and Strike Out Orders
Legal Issues
- 1 ['Whether the costs order made in favour of the plaintiff on 29 October 2021 should be vacated and replaced with no order as to the costs of the motion.' "Whether the parties' partial success on the plaintiff's motion justified departing from the ordinary costs order."]
Ratio Decidendi
The defendant's application was refused because the plaintiff had obtained a final judgment on Payment Claim 13, succeeded on the strike out aspects of the motion, and faced withdrawn or failed challenges by the defendant; the plaintiff's substantial success justified a favourable costs order despite the defendant preserving its defence to Payment Claim 14.
Court Disposition
Defendant's application refused; orders made on 29 October 2021 confirmed; defendant ordered to pay the costs of the application to vacate and vary the costs order.
Orders
- ["Defendant's application is refused." 'Confirm the orders made on 29 October 2021.' "Order the defendant to pay the costs of the defendant's application to vacate and vary the costs order."]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment