Jem Developments v Hansen Yuncken [2006] NSWSC 1308

Jem Developments v Hansen Yuncken [2006] NSWSC 1308

Clause 2.1(2) of the settlement deed precludes Jempac from setting off its claims in connection with the project (including damages for delay or defects) against the $500,000 payment obligation; there is therefore no offsetting claim available under s 459H, and the application to set aside the statutory demand fails on this basis.

Parties
Plaintiff: Jem Developments Pty Ltd; Plaintiff: Pacifico Holdings Pty Ltd; Defendant: Hansen Yuncken Pty Ltd
Jurisdiction
Australia
Judgment Date
04 December 2006
Procedural Posture
Corporations Application (statutory Demand) / Judgment Following Hearing of Application to Set Aside Statutory Demand
Outcome
Application to set aside statutory demand dismissed, period for compliance with demand extended, costs to the defendant.
Legal Topics
Statutory Demand, Offsetting Claim, Construction of Contract, Abuse of Process, Dispute Resolution Clauses, Liquidated Damages

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 11
Sign in to unlock

Parties

Jem Developments Pty Ltd

Plaintiff

Pacifico Holdings Pty Ltd

Plaintiff

Hansen Yuncken Pty Ltd

Defendant

Procedural Posture

Corporations Application (statutory Demand) / Judgment Following Hearing of Application to Set Aside Statutory Demand

  1. 1 Whether Jempac has an offsetting claim against Hansen Yuncken capable of setting aside statutory demand under s 459H of the Corporations Act 2001 (Cth)
  2. 2 Proper construction of clause 2.1(2) of the settlement deed: does it prevent set-off of Jempac’s claims against the $500,000 claim by Hansen Yuncken?
  3. 3 Whether the statutory demand should be set aside on other grounds (s 459J): abuse of process or failure to follow contractual dispute resolution procedures

Ratio Decidendi

Clause 2.1(2) of the settlement deed precludes Jempac from setting off its claims in connection with the project (including damages for delay or defects) against the $500,000 payment obligation; there is therefore no offsetting claim available under s 459H, and the application to set aside the statutory demand fails on this basis.

Court Disposition

Application to set aside statutory demand dismissed, period for compliance with demand extended, costs to the defendant.

Orders

  • Under s 459F(2)(a), period for compliance with the statutory demand served on 23 March 2006 extended up to and including 18 December 2006.
  • Originating process otherwise dismissed.