Burrell v JGE Machinery [2014] NSWSC 19

Burrell v JGE Machinery [2014] NSWSC 19

There is a serious question to be tried as to whether the adjudication determination was made within the time requirements of the Act, whether jurisdictional preconditions were satisfied, and whether a valid contract existed; balance of convenience supports grant of interlocutory relief, subject to payment in of the adjudicated amount.

Jurisdiction
Australia
Judgment Date
24 January 2014
Procedural Posture
Interlocutory Proceedings / Application for Interlocutory Injunction
Outcome
Interlocutory injunction granted on condition as to payment in of adjudicated amount.
Legal Topics
['interlocutory Injunctions' 'adjudication Determination' 'security of Payment Act' 'remuneration Under Building Contracts']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Interlocutory Proceedings / Application for Interlocutory Injunction

  1. 1 ['Whether to grant interlocutory injunctive relief to restrain enforcement of adjudication determination' 'Compliance with s 17 notice requirements' 'Whether adjudication determination was made within 12 months after last construction work as required by s 13(4)(b) of the Act' 'Whether there was a construction contract between plaintiff and first defendant' 'Risk of insolvency as a ground for restraint']

Ratio Decidendi

There is a serious question to be tried as to whether the adjudication determination was made within the time requirements of the Act, whether jurisdictional preconditions were satisfied, and whether a valid contract existed; balance of convenience supports grant of interlocutory relief, subject to payment in of the adjudicated amount.

Court Disposition

Interlocutory injunction granted on condition as to payment in of adjudicated amount.

Orders

  • ['Proceedings entered into Technology and Construction List.' 'Matter stood over to motions list on 14 February 2014.' 'Orders in accordance with form of order amended and initialled by judge and dated 24 January 2014.' 'Orders lapse automatically if plaintiff fails to comply with undertakings.' 'Notice of orders to...