Jonathan Martin & Anor v Roads and Maritime Services [2017] NSWLEC 1162
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Acting Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the Court was required to dispose of the proceedings in accordance with that agreement.
- Jurisdiction
- Australia
- Judgment Date
- 29 March 2017
- Procedural Posture
- Class 3 Compulsory Acquisition of Land Compensation Proceedings / Conciliation Conference; Orders by Agreement Under S 34(3) of the Land and Environment Court Act 1979
- Outcome
- Proceedings disposed of in accordance with the parties' agreement; compensation determined in the sum of $671,775.00 and ancillary orders made.
- Legal Topics
- ['just Terms Compensation' 'conciliation Conference' 'consent Orders' 'section 34 Agreement']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 3 Compulsory Acquisition of Land Compensation Proceedings / Conciliation Conference; Orders by Agreement Under S 34(3) of the Land and Environment Court Act 1979
Legal Issues
- 1 ['Whether the parties had reached an agreement under s 34(3) of the Land and Environment Court Act 1979 as to terms of a decision acceptable to them.' 'Whether the agreed decision was one the Court could have made in the proper exercise of its functions.' 'The amount and terms of compensation for the acquisition of the identified land and easement.']
Ratio Decidendi
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Acting Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the Court was required to dispose of the proceedings in accordance with that agreement.
Court Disposition
Proceedings disposed of in accordance with the parties' agreement; compensation determined in the sum of $671,775.00 and ancillary orders made.
Orders
- ['Compensation is determined in the sum of $671,775.00, pursuant to section 55 of the Land Acquisition (Just Terms Compensation) Act 1991, for the acquisition of Lot 13 in Deposited Plan 1217247, being part of the land in Certificate of Title 12/249262 known as 1472 The Northern Road, Bringelly and an easement in...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment