Chandra v Bunnings Group Ltd [2009] NSWDC 194

Chandra v Bunnings Group Ltd [2009] NSWDC 194

The defendant, as occupier, was negligent in permitting forklift tines to be concealed by pooled water on a pedestrian access route, creating a non-obvious, foreseeable risk of harm to the plaintiff, who acted reasonably and with due care. The risk was not 'obvious' as defined by s 5F of the Civil Liability Act 2002, and there was no contributory negligence on the plaintiff's part. The plaintiff's injuries and claimed losses are causally linked to the defendant's negligence, justifying the award of damages assessed; procedural timelines under case management rules were correctly enforced.

Jurisdiction
Australia
Judgment Date
06 November 2009
Procedural Posture
Civil / Judgment After Trial
Outcome
Verdict and judgment for the plaintiff. Defendant to pay the plaintiff's costs.
Legal Topics
['negligence' "occupier's Liability" 'slip and Fall' 'obvious Risk' 'contributory Negligence' 'damages' 'adjournment']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Civil / Judgment After Trial

  1. 1 ["Was the plaintiff's fall due to negligence on the part of the defendant?" 'Was there contributory negligence on the part of the plaintiff?' "Was the risk to which the plaintiff was exposed an 'obvious risk' within the meaning of s 5F of the Civil Liability Act 2002?" "Whether there should be a reduction in the plaintiff's entitlement to damages pursuant to s 151Z(2) of the Workers' Compensation Act 1987?" 'Assessment of the claimed heads of damage.']

Ratio Decidendi

The defendant, as occupier, was negligent in permitting forklift tines to be concealed by pooled water on a pedestrian access route, creating a non-obvious, foreseeable risk of harm to the plaintiff, who acted reasonably and with due care. The risk was not 'obvious' as defined by s 5F of the Civil Liability Act 2002, and there was no contributory negligence on the plaintiff's part. The plaintiff's injuries and claimed losses are causally linked to the defendant's negligence, justifying the award of damages assessed; procedural timelines under case management rules were correctly enforced.

Court Disposition

Verdict and judgment for the plaintiff. Defendant to pay the plaintiff's costs.

Orders

  • ['Verdict and judgment for the plaintiff in the sum of $402,624.' "Defendant to pay the plaintiff's costs." 'Exhibits may be returned.' 'Liberty to apply on 7 days notice if further orders are required.']