Joye Group Pty Limited v Cemco Projects Pty Limited [2021] NSWDC 151
The defendant's email of 8 May 2020 satisfied the requirements of a payment schedule under s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) in respect of Invoices JS19794 and JSA19293, by identifying the invoices, stating that no payment would be made until works were completed, and articulating the reason for withholding payment. Accordingly, the plaintiff is not entitled to judgment for these invoices. In relation to Invoices JS19774 and JSA19284, the defendant failed to provide a payment schedule, and the plaintiff is entitled to judgment for those amounts.
- Jurisdiction
- Australia
- Judgment Date
- 30 April 2021
- Procedural Posture
- Civil / Principal Judgment
- Outcome
- Partly in favour of plaintiff, partly in favour of defendant
- Legal Topics
- ['payment Schedules' 'building and Construction Industry Security of Payment Act 1999' 'requirements of Payment Claims' 'identification of Payment Claims' 'reasons for Withholding Payment']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil / Principal Judgment
Legal Issues
- 1 ["Whether the defendant provided a valid payment schedule under s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) in response to the plaintiff's payment claims" 'Whether the plaintiff is entitled to judgment for unpaid invoices under the Act']
Ratio Decidendi
The defendant's email of 8 May 2020 satisfied the requirements of a payment schedule under s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) in respect of Invoices JS19794 and JSA19293, by identifying the invoices, stating that no payment would be made until works were completed, and articulating the reason for withholding payment. Accordingly, the plaintiff is not entitled to judgment for these invoices. In relation to Invoices JS19774 and JSA19284, the defendant failed to provide a payment schedule, and the plaintiff is entitled to judgment for those amounts.
Court Disposition
Partly in favour of plaintiff, partly in favour of defendant
Orders
- ['Judgment for the plaintiff against the defendant in the sum of $46,322.36.' 'Judgment for the defendant against the plaintiff with regard to Invoices JSA 19293 and JS 19794.' 'Parties may contact the associate within 14 days to relist the matter for argument regarding any various orders, interest and costs, if not...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment