Assabgy v Hunter's Hill Council [2016] NSWLEC 1449
As the parties reached agreement at conciliation and the Court was satisfied the decision could have been made in the proper exercise of its functions, the Court disposed of the proceedings in accordance with that agreement.
- Jurisdiction
- Australia
- Judgment Date
- 26 September 2016
- Procedural Posture
- Class 1 / Conciliation Conference and Final Orders
- Outcome
- Appeal upheld and development application approved subject to conditions and payment of costs.
- Legal Topics
- ['development Application' 'conciliation' 'approval Process']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 1 / Conciliation Conference and Final Orders
Legal Issues
- 1 ["Whether the parties' agreement at conciliation conference should be given effect as an order of the Court under s 34(3) of the Land and Environment Court Act 1979"]
Ratio Decidendi
As the parties reached agreement at conciliation and the Court was satisfied the decision could have been made in the proper exercise of its functions, the Court disposed of the proceedings in accordance with that agreement.
Court Disposition
Appeal upheld and development application approved subject to conditions and payment of costs.
Orders
- ['Applicant granted leave to rely on specified documents for DA2015/1136.' "Applicant to pay respondent's costs in the amount of $1,500 under section 97B of the Environmental Planning and Assessment Act 1979." 'Appeal upheld.' 'Development Application DA2015/1136 for demolition and construction at 18 Farnell Street,...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment