K & K Quality Constructions Pty Ltd v Issa [2019] NSWCATCD 65
It is just and equitable to order payment for documented preliminary work (architectural, structural, stormwater plans and survey) performed in relation to residential building work, even absent a written contract, where the respondent's conduct and signed documents indicated awareness and approval that such work would be undertaken. Recovery for other items is denied due to insufficient evidence of value or approval.
- Jurisdiction
- Australia
- Judgment Date
- 05 November 2019
- Procedural Posture
- Home Building Application / Final Hearing and Determination
- Outcome
- Money order granted for part of applicant's claim; respondent required to pay for documented items only.
- Legal Topics
- ['quantum Meruit' 'entitlement to Payment Without Written Contract' 'consumer Claims for Residential Building Work' 'just and Equitable Remedies']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Application / Final Hearing and Determination
Legal Issues
- 1 ['Whether the applicant is entitled to payment for preliminary residential building work without a written contract' 'Whether a binding agreement existed between the parties for preliminary work' 'Whether quantum meruit applies and if recovery is just and equitable']
Ratio Decidendi
It is just and equitable to order payment for documented preliminary work (architectural, structural, stormwater plans and survey) performed in relation to residential building work, even absent a written contract, where the respondent's conduct and signed documents indicated awareness and approval that such work would be undertaken. Recovery for other items is denied due to insufficient evidence of value or approval.
Court Disposition
Money order granted for part of applicant's claim; respondent required to pay for documented items only.
Orders
- ['The respondent is to pay the applicant the sum of $6,270 on or before 30 November 2019.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment