Pawar v Willoughby Homes Pty Ltd [2021] NSWCATCD 161
The Tribunal found that, although the builder contributed to some delays, the owner's conduct caused or significantly contributed to the delays that prevented rectification within the original 12-week period. The builder remained ready, willing and able to do the required work, and it would be unjust to grant the owner a money order in circumstances where he contributed to non-compliance. Accordingly, a further work order is appropriate, with additional safeguards (detailed schedule, method statement, independent expert, etc.) to ensure completion. Only the claim for carpet replacement is allowed as a money order.
- Jurisdiction
- Australia
- Judgment Date
- 04 March 2021
- Procedural Posture
- Renewal Proceeding (building Claim) / Final Hearing and Decision
- Outcome
- Work order granted; limited money order for carpet replacement; directions for further applications as to costs.
- Legal Topics
- ['home Building Defects' 'work Order Vs Money Order' 'renewal of Proceedings' 'case Management' 'expert Evidence' 'enforcement of Tribunal Orders']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Renewal Proceeding (building Claim) / Final Hearing and Decision
Legal Issues
- 1 ['Whether a work order or money order should be granted due to non-compliance with prior orders' 'Who caused the delay in completion of rectification work' 'Appropriate remedy for non-compliance with consent orders']
Ratio Decidendi
The Tribunal found that, although the builder contributed to some delays, the owner's conduct caused or significantly contributed to the delays that prevented rectification within the original 12-week period. The builder remained ready, willing and able to do the required work, and it would be unjust to grant the owner a money order in circumstances where he contributed to non-compliance. Accordingly, a further work order is appropriate, with additional safeguards (detailed schedule, method statement, independent expert, etc.) to ensure completion. Only the claim for carpet replacement is allowed as a money order.
Court Disposition
Work order granted; limited money order for carpet replacement; directions for further applications as to costs.
Orders
- ["The builder is to carry out rectification work in a proper and workmanlike manner in relation to defects identified as Items 1 to 10 (inclusive) and 25 in Mr O'Donnell's 24 June 2019 report." "Mr O'Donnell (or his nominee if unavailable) to act as independent expert overseeing rectification work." 'All...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment