Karen Frances Anne Blackley v Lane Cove Municipal Council [2016] NSWLEC 1654
The Court, having received an agreement acceptable to the parties at or after a conciliation conference and being satisfied that the decision is one that the Court could have made properly, must dispose of the proceedings and make orders in accordance with that agreement pursuant to s 34(3)(a) of the Land and Environment Court Act 1979.
- Parties
- Applicant: Karen Frances Anne Blackley; Respondent: Lane Cove Council
- Jurisdiction
- Australia
- Judgment Date
- 25 January 2017
- Procedural Posture
- Class 1 / Conciliation Conference; Final Orders Following Agreement
- Outcome
- Orders made by consent in accordance with agreement under s 34(3) Land and Environment Court Act 1979; proceedings disposed of as agreed.
- Legal Topics
- Development Application, Conciliation Conference, Revocation of Council Order, Building Certificate, Agreement Between Parties
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Karen Frances Anne Blackley
Applicant
Lane Cove Council
Respondent
Procedural Posture
Class 1 / Conciliation Conference; Final Orders Following Agreement
Legal Issues
- 1 Whether agreement between parties regarding development application and council orders could be given effect under s 34(3) of the Land and Environment Court Act 1979
Ratio Decidendi
The Court, having received an agreement acceptable to the parties at or after a conciliation conference and being satisfied that the decision is one that the Court could have made properly, must dispose of the proceedings and make orders in accordance with that agreement pursuant to s 34(3)(a) of the Land and Environment Court Act 1979.
Court Disposition
Orders made by consent in accordance with agreement under s 34(3) Land and Environment Court Act 1979; proceedings disposed of as agreed.
Orders
- Council Order issued under s.121B of the Environmental Planning and Assessment Act 1979 dated 7 June 2016 shall be revoked upon the approval of a Building Certificate for the constructed retaining wall, timber deck and associated earth works at 14 Pengilly Street, Riverview.
- Council's Order issued under s.121B of the Environmental Planning and Assessment Act 1979 dated 7 June 2016 is stayed until the earlier of: 12 January 2018 or completion of the works approved by Sydney Water on 12 January 2017 or confirmation such works are not required.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment