Kosciusko Alpine Club Limited v National Parks and Wildlife Service [1988] NSWLEC 122
The undertaking should be partially released because the works required by the First Respondent were exclusively directed to rendering the existing partial structure and building site safe, were minor works that did not realistically constitute a continuation of the building work, and would not materially affect the status quo or prejudice any future approval decision.
- Jurisdiction
- Australia
- Judgment Date
- 01 June 1988
- Procedural Posture
- Class 4 Proceedings; Amended Notice of Motion / Urgent Motion by the Second Respondent for Partial Release From an Undertaking Given to the Court After the Class 4 Proceedings Were Concluded
- Outcome
- Amended Notice of Motion granted; Second Respondent partially released from its undertaking.
- Legal Topics
- ['partial Release From Undertaking' 'interlocutory Injunction' 'ski Lodge Building Approval' 'public Safety' 'temporary Safety Works']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 4 Proceedings; Amended Notice of Motion / Urgent Motion by the Second Respondent for Partial Release From an Undertaking Given to the Court After the Class 4 Proceedings Were Concluded
Legal Issues
- 1 ['Whether the Second Respondent should be partially released from its undertaking to enable it to undertake works specified by the National Parks and Wildlife Service.' 'Whether public safety required dismantling and removal of the steel structure rather than the proposed safety works.' 'Whether permitting the works would sanction illegal building works or prejudice any future decision on approval of the ski lodge building complex.']
Ratio Decidendi
The undertaking should be partially released because the works required by the First Respondent were exclusively directed to rendering the existing partial structure and building site safe, were minor works that did not realistically constitute a continuation of the building work, and would not materially affect the status quo or prejudice any future approval decision.
Court Disposition
Amended Notice of Motion granted; Second Respondent partially released from its undertaking.
Orders
- ['The Second Respondent is released from its undertaking given to the Court on 22 April 1988, but only so as to enable it to execute the works being items 1 to 11 inclusive specified by the National Parks and Wildlife Service in its letter dated 27 May 1988 to Phil McMaster, Architects.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment