Landmark Group Australia Pty Limited v Lane Cove Council [2019] NSWLEC 1034

Landmark Group Australia Pty Limited v Lane Cove Council [2019] NSWLEC 1034

The proposed development does not create isolated sites within the DCP meaning; variation to the height standard is justified based on site-specific grounds; permissible uses on adjoining sites remain viable; the application satisfies statutory and local planning requirements, including the objectives of the relevant standards and zone; consent should be granted and the appeal upheld.

Jurisdiction
Australia
Judgment Date
05 February 2019
Procedural Posture
Appeal / Final Judgment
Outcome
Appeal upheld; development consent granted
Legal Topics
['development Application' 'site Isolation' 'variation to Development Standards' 'consent Conditions' 'urban Design' 'minimum Site Area']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal / Final Judgment

  1. 1 ['Whether the proposed development creates isolated sites within the meaning of the planning controls' 'Whether variation to the height and minimum site area standards is justified' 'Whether consent should be granted for demolition and residential flat building construction']

Ratio Decidendi

The proposed development does not create isolated sites within the DCP meaning; variation to the height standard is justified based on site-specific grounds; permissible uses on adjoining sites remain viable; the application satisfies statutory and local planning requirements, including the objectives of the relevant standards and zone; consent should be granted and the appeal upheld.

Court Disposition

Appeal upheld; development consent granted

Orders

  • ['Applicant granted leave to rely on plans in Exhibit A' "Applicant to pay Respondent's costs thrown away due to amendment ($1,000) within 28 days pursuant to s 8.15(3) EPA Act 1979" 'Request to vary development standard in clause 4.3 Lane Cove LEP 2009 upheld' 'Appeal upheld' 'Development Application DA/86/2017 for...