Lanmac (NSW-ACT) Pty Limited v Andrew Bruce Wallace & Ors [2010] NSWSC 976
The plaintiff's application was an attempt to avoid the requirement to provide security before seeking to restrain enforcement of adjudication determinations; absent undertakings or bank guarantee, the proceedings should be stayed until Plaintiff pays the adjudicated amounts and costs into Court or provides a satisfactory bank guarantee, and injunctive orders should be dissolved.
- Parties
- Plaintiff: Lanmac (NSW-ACT) Pty Limited; First Defendant: Andrew Bruce Wallace; Second Defendant: Able Adjudication Pty Limited; Third Defendant: CMS Group Pty Limited
- Jurisdiction
- Australia
- Judgment Date
- 27 August 2010
- Procedural Posture
- Equity Technology and Construction List / Interlocutory Application Ex Tempore Judgment on Notice of Motion (injunctive Relief, Stay)
- Outcome
- Plaintiff's application for injunctions refused; proceedings stayed unless and until payment into Court or provision of bank guarantee for adjudicated amounts and costs; costs awarded to third defendant; injunctive orders dissolved; further listing vacated.
- Legal Topics
- Security of Payment, Injunctions, Stay of Proceedings, Bank Guarantee/bonding, Adjudication Enforcement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lanmac (NSW-ACT) Pty Limited
Plaintiff
Andrew Bruce Wallace
First Defendant
Able Adjudication Pty Limited
Second Defendant
CMS Group Pty Limited
Third Defendant
Procedural Posture
Equity Technology and Construction List / Interlocutory Application Ex Tempore Judgment on Notice of Motion (injunctive Relief, Stay)
Legal Issues
- 1 Whether plaintiff can restrain enforcement of adjudication determinations under the Building and Construction Industry Security of Payment Act 1999 (NSW) without providing security or bank guarantee
- 2 Whether the proceedings should be stayed until payment into Court or provision of a bank guarantee for the adjudicated amounts and costs
Ratio Decidendi
The plaintiff's application was an attempt to avoid the requirement to provide security before seeking to restrain enforcement of adjudication determinations; absent undertakings or bank guarantee, the proceedings should be stayed until Plaintiff pays the adjudicated amounts and costs into Court or provides a satisfactory bank guarantee, and injunctive orders should be dissolved.
Court Disposition
Plaintiff's application for injunctions refused; proceedings stayed unless and until payment into Court or provision of bank guarantee for adjudicated amounts and costs; costs awarded to third defendant; injunctive orders dissolved; further listing vacated.
Orders
- The injunctions issued on 20 August 2010 and extended on 27 August 2010 dissolved.
- Pursuant to s 67 of the Civil Procedure Act 2005, proceedings stayed until payment into Court by the plaintiff of the amounts of the two adjudication determinations and adjudicator’s costs, or provision of a bank guarantee acceptable to the Court but payable to the third defendant for those amounts.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment