Middleton v Wrona [2023] NSWCATAP 158
The Tribunal erred in ordering restitution of $65,280.59 based only on credits for particular items without conducting a proper accounting of all works performed under the contract and assessing whether homeowners paid more than was properly due for the works; the evidence and findings did not establish overpayment or unjust enrichment, and the builder was entitled to retain the payments made. The demolition and rebuild of the garage order was supported by expert evidence accepted by the Tribunal as findings of defect and unsuitability for intended load/use.
- Parties
- Appellant: Lee Kenneth Middleton; First Respondent: Linda May Wrona; Second Respondent: Richard John Wrona
- Jurisdiction
- Australia
- Judgment Date
- 14 June 2023
- Procedural Posture
- Civil Appeal / Appeal Panel Decision
- Outcome
- Appeal allowed in part; order 3 for restitution set aside; garage work order upheld; leave to appeal otherwise refused; costs submissions invited.
- Legal Topics
- Lump Sum Contract, Variation, Progress Payments, Breach of Contract, Rectification, Money Had and Received, Unjust Enrichment, Garage Demolition and Rebuild
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lee Kenneth Middleton
Appellant
Linda May Wrona
First Respondent
Richard John Wrona
Second Respondent
Procedural Posture
Civil Appeal / Appeal Panel Decision
Legal Issues
- 1 Whether restitution award for overpayment under renovation contract was appropriate
- 2 Whether builder was required to demolish and rebuild garage due to defects
- 3 Proper characterization of progress payments and additional works under contract
Ratio Decidendi
The Tribunal erred in ordering restitution of $65,280.59 based only on credits for particular items without conducting a proper accounting of all works performed under the contract and assessing whether homeowners paid more than was properly due for the works; the evidence and findings did not establish overpayment or unjust enrichment, and the builder was entitled to retain the payments made. The demolition and rebuild of the garage order was supported by expert evidence accepted by the Tribunal as findings of defect and unsuitability for intended load/use.
Court Disposition
Appeal allowed in part; order 3 for restitution set aside; garage work order upheld; leave to appeal otherwise refused; costs submissions invited.
Orders
- Leave to appeal order 3 granted; appeal allowed and order 3 is set aside.
- Stay of order 1 lifted; order 4(1)(f) varied so garage work completion required within 9 months from date of order.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment