Lewance Construction Pty Ltd -v- Southern Han Breakfast Point Pty Ltd [2014] NSWSC 1726
The evidence supported that Mr McMahon was authorised by SHBP to provide the payment schedule in reply to the payment claim for progress claim 15; therefore, SHBP provided a payment schedule within the prescribed period and is not liable under s 15 of the Act.
- Jurisdiction
- Australia
- Judgment Date
- 04 December 2014
- Procedural Posture
- Principal Judgment / Final Judgment
- Outcome
- Plaintiff's Summons dismissed
- Legal Topics
- ['building Contracts' 'payment Schedules' 'authority of Agent']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Principal Judgment / Final Judgment
Legal Issues
- 1 ['Whether payment schedule was provided by the authorised agent of the respondent under s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW)' 'Whether payment schedule was provided within the prescribed time']
Ratio Decidendi
The evidence supported that Mr McMahon was authorised by SHBP to provide the payment schedule in reply to the payment claim for progress claim 15; therefore, SHBP provided a payment schedule within the prescribed period and is not liable under s 15 of the Act.
Court Disposition
Plaintiff's Summons dismissed
Orders
- ["The plaintiff's Summons be dismissed" "The plaintiff pay the first defendant's costs"]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment