Lilie Jurleta v Zhong Xing Liu [2017] NSWSC 1015

Lilie Jurleta v Zhong Xing Liu [2017] NSWSC 1015

The plaintiff was entitled to orders effecting specific performance because the Agreement and Scope of Works Plan were sufficiently certain as to the intended location of the easement, the survey plans conformed with that location, the defendant could not identify any discrepancy, the sewer-pipe concern did not...

Source-derived case information.

Jurisdiction
Australia
Judgment Date
21 July 2017
Procedural Posture
Equity Proceedings Concerning Enforcement of an Agreement for the Grant of an Easement / Ex Tempore Principal Judgment on Hearing of Summons
Outcome
Orders made for specific performance of the agreement for the grant of an easement; defendant ordered to pay the plaintiff's costs on the ordinary basis.
Legal Topics
['torrens Title' 'easements' 'specific Performance' 'registration of Easement']
['real Property' 'equity'] ['torrens Title' 'easements' 'specific Performance' 'registration of Easement']

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Equity Proceedings Concerning Enforcement of an Agreement for the Grant of an Easement / Ex Tempore Principal Judgment on Hearing of Summons

  1. 1 ['Whether the agreement for the grant of an easement should be specifically enforced.' 'Whether the location of the proposed easement and drainage pipes was too uncertain because of the photographs and plans annexed to the agreement.' 'Whether the existence of sewer pipes in the servient tenement justified refusal or variation of the orders sought.' 'Whether costs incurred by the defendant in relation to solicitors or interpreters were a bar to specific performance.']

Ratio Decidendi

The plaintiff was entitled to orders effecting specific performance because the Agreement and Scope of Works Plan were sufficiently certain as to the intended location of the easement, the survey plans conformed with that location, the defendant could not identify any discrepancy, the sewer-pipe concern did not provide a basis to refuse the orders and was addressed by the plaintiff's undertaking, and the claimed litigation-related costs did not fall within cl 10 of the Agreement or bar performance.

Court Disposition

Orders made for specific performance of the agreement for the grant of an easement; defendant ordered to pay the plaintiff's costs on the ordinary basis.

Orders

  • ['Within 7 days of the date of this order, the Defendant sign the original of the plans, a copy of which is Exhibit 5, and provide the signed plans to the Plaintiff to enable them to be lodged with Land and Property Information (LPI).' 'Within 7 days of the date of this order, the Defendant produce to the Plaintiff...