Tabachnik v Waverley Council [2020] NSWLEC 1231

Tabachnik v Waverley Council [2020] NSWLEC 1231

The court upheld the appeal and granted consent to the proposed development as all jurisdictional prerequisites were satisfied, the written request for variation of the Floor Space Ratio standard was well founded, and the parties reached agreement within the court's proper exercise of functions.

Jurisdiction
Australia
Judgment Date
28 May 2020
Procedural Posture
Appeal / Conciliation Conference and Final Orders
Outcome
Appeal upheld; development application approved subject to conditions.
Legal Topics
['development Application' 'floor Space Ratio' 'variation of Development Standards' 'environmental Planning' 'jurisdictional Prerequisites']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal / Conciliation Conference and Final Orders

  1. 1 ['Whether the proposed development complies with relevant planning standards and statutory requirements' 'Whether jurisdictional prerequisites for granting development consent are satisfied' "Whether the applicant's request to vary the floor space ratio standard is well founded"]

Ratio Decidendi

The court upheld the appeal and granted consent to the proposed development as all jurisdictional prerequisites were satisfied, the written request for variation of the Floor Space Ratio standard was well founded, and the parties reached agreement within the court's proper exercise of functions.

Court Disposition

Appeal upheld; development application approved subject to conditions.

Orders

  • ["The applicant's clause 4.6 request in relation to the floor space ratio development standard pursuant to cl 4.4A of the Waverley Local Environmental Plan 2012 is well founded and upheld." 'The appeal is upheld.' "Development Application DA 35/2019 for demolition of existing dwelling and construction of an attached...