Matthew Arthur Harrison trading as All Town Skips v Central Coast Council [2022] NSWLEC 1244

Matthew Arthur Harrison trading as All Town Skips v Central Coast Council [2022] NSWLEC 1244

Because the parties agreed to disposition of the proceedings, and the Court was satisfied that it had jurisdiction and that the relevant statutory and planning prerequisites were met or would be addressed by conditions, the Court was required under s 34 of the Land and Environment Court Act 1979 to dispose of the matter in accordance with the parties' agreement by upholding the appeal and granting conditional development consent.

Jurisdiction
Australia
Judgment Date
11 May 2022
Procedural Posture
Class 1 Appeal Against Refusal of Development Application Da/914/2019 / Resolved by Conciliation Conference Under S 34(1) of the Land and Environment Court Act 1979
Outcome
Appeal upheld; development consent granted subject to conditions at Annexure A.
Legal Topics
['development Application' 'waste or Resource Transfer Station' 'road Access' 'conciliation Conference' 'development Consent']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 Appeal Against Refusal of Development Application Da/914/2019 / Resolved by Conciliation Conference Under S 34(1) of the Land and Environment Court Act 1979

  1. 1 ["Whether the Court had jurisdiction under s 34 of the Land and Environment Court Act 1979 to dispose of the proceedings in accordance with the parties' agreement." 'Whether development consent could be granted for a waste or resource transfer station and ancillary works at 5 Mooramba Avenue, Tuggerah, subject to conditions.' 'Whether relevant planning controls and environmental matters, including owner consent, permissibility, acid sulphate soils, essential services, contamination, bushfire risk and ecology, were satisfactorily addressed.']

Ratio Decidendi

Because the parties agreed to disposition of the proceedings, and the Court was satisfied that it had jurisdiction and that the relevant statutory and planning prerequisites were met or would be addressed by conditions, the Court was required under s 34 of the Land and Environment Court Act 1979 to dispose of the matter in accordance with the parties' agreement by upholding the appeal and granting conditional development consent.

Court Disposition

Appeal upheld; development consent granted subject to conditions at Annexure A.

Orders

  • ['The appeal is upheld.' 'Development consent is granted to development application DA/914/2019 for the construction of a waste or resource transfer station and ancillary works at 5 Mooramba Avenue, Tuggerah, subject to the conditions at Annexure A.']