MKD Architects Pty Ltd v Randwick City Council [2016] NSWLEC 1059

MKD Architects Pty Ltd v Randwick City Council [2016] NSWLEC 1059

The parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 as to the terms of a decision acceptable to them, and the Commissioner was satisfied that the decision was one the Court could have made in the proper exercise of its functions; accordingly, the proceedings were to be disposed of in accordance with that decision.

Jurisdiction
Australia
Judgment Date
18 February 2016
Procedural Posture
Class 1 / Conciliation Conference
Outcome
Proceedings disposed of in accordance with the parties' agreement.
Legal Topics
['conciliation Conference' 'agreement Between the Parties' 'orders Under S 34(3) of the Land and Environment Court Act 1979']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 / Conciliation Conference

  1. 1 ['Whether the agreement reached between the parties under s 34(3) of the Land and Environment Court Act 1979 was a decision the Court could have made in the proper exercise of its functions.']

Ratio Decidendi

The parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 as to the terms of a decision acceptable to them, and the Commissioner was satisfied that the decision was one the Court could have made in the proper exercise of its functions; accordingly, the proceedings were to be disposed of in accordance with that decision.

Court Disposition

Proceedings disposed of in accordance with the parties' agreement.

Orders

  • ["Final orders to give effect to the parties' agreement were made on 18 February 2016."]