Modern Building Solutions Pty Ltd v Fine Touch Pty Ltd [2021] NSWDC 451
The Court preferred the evidence of Mr Philip Makrys over that of Irek and Matthew Kaminski. The payment history, progress invoices calculated by reference to percentages of $187,000, the cheque and handwritten notations, and the 21 December 2017 meeting document supported a finding that the initial hourly arrangement ended after invoice 244 and that the parties agreed on 15 August 2017 to a fixed price contract of $170,000 plus GST, later adjusted and finalised. The plaintiff accepted the final outstanding amount of $45,100, which was paid, so the plaintiff failed to establish the alleged unpaid hourly-rate entitlement.
- Jurisdiction
- Australia
- Judgment Date
- 12 May 2021
- Procedural Posture
- Civil Action for Damages for Breach of Contract / Principal Judgment After Hearing
- Outcome
- Judgment for the Defendant.
- Legal Topics
- ['breach of Contract' 'building Work Subcontract' 'hourly Rate or Day Labour Agreement' 'fixed Price Contract' 'contract Variations' 'accord and Satisfaction' 'conflict of Evidence']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil Action for Damages for Breach of Contract / Principal Judgment After Hearing
Legal Issues
- 1 ["Whether the plaintiff's work for the defendant on the St Patrick's Green project was to be paid on an hourly/day labour basis or under a fixed price contract varied from time to time." 'Whether an agreement was reached on 15 August 2017 for a fixed price of $170,000 plus GST for the relevant painting works.' 'Whether later meetings and payments, including the payment of $45,100 on 21 December 2017, resolved the amount outstanding or amounted to accord and satisfaction.']
Ratio Decidendi
The Court preferred the evidence of Mr Philip Makrys over that of Irek and Matthew Kaminski. The payment history, progress invoices calculated by reference to percentages of $187,000, the cheque and handwritten notations, and the 21 December 2017 meeting document supported a finding that the initial hourly arrangement ended after invoice 244 and that the parties agreed on 15 August 2017 to a fixed price contract of $170,000 plus GST, later adjusted and finalised. The plaintiff accepted the final outstanding amount of $45,100, which was paid, so the plaintiff failed to establish the alleged unpaid hourly-rate entitlement.
Court Disposition
Judgment for the Defendant.
Orders
- ['Judgment for the defendant against the plaintiff.' "The plaintiff is to pay the defendant's costs."]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment