An agreement acceptable to the parties was reached during a conciliation conference and, being satisfied that the decision could properly be made by the Court, the proceedings were disposed of in accordance with s 34(3) of the Land and Environment Court Act 1979.

Jurisdiction
Australia
Judgment Date
21 September 2016
Procedural Posture
Class 1 / Final Orders Following Conciliation Conference
Outcome
Appeal upheld; development application approved subject to conditions.
Legal Topics
['development Application' 'conciliation Conference' 'section 34 Agreement']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 / Final Orders Following Conciliation Conference

  1. 1 ['Whether the Court can make orders by consent under s 34(3) of the Land and Environment Court Act 1979 based on agreement between parties concerning a development application']

Ratio Decidendi

An agreement acceptable to the parties was reached during a conciliation conference and, being satisfied that the decision could properly be made by the Court, the proceedings were disposed of in accordance with s 34(3) of the Land and Environment Court Act 1979.

Court Disposition

Appeal upheld; development application approved subject to conditions.

Orders

  • ['Leave granted to the applicant to rely on amended plans prepared by Cracknell & Lonergan Architects as specified.' 'The appeal is upheld.' 'Development application 102/2016 is approved, subject to the conditions in annexure A.']