Clemesha v Mosman Municipal Council [2021] NSWLEC 1002
The Court finds the development control order was valid when made, but is satisfied to modify it in light of agreement between the parties and additional compliance works, including stormwater drainage and remedial actions for bushfire safety. The modified development control order and remedial works address Council concerns and legal requirements, justifying both the amended demolition/retention orders and directing the issue of a Building Information Certificate upon compliance.
- Jurisdiction
- Australia
- Judgment Date
- 05 January 2021
- Procedural Posture
- Appeal / Judgment After Hearing
- Outcome
- Appeal upheld (both proceedings); development control order modified; Building Information Certificate to be issued upon compliance
- Legal Topics
- ['development Control Order' 'building Information Certificate' 'stormwater Drainage' 'unapproved Structures' 'crown Land Management']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Appeal / Judgment After Hearing
Legal Issues
- 1 ['Whether the development control order requiring demolition of retaining wall, shed, and stairs was lawfully issued and should be upheld, modified or revoked' 'Whether Building Information Certificate should be issued after provision of further information and remedial works' 'Whether amended works would unreasonably impact stormwater flow or values of the adjoining Reserve']
Ratio Decidendi
The Court finds the development control order was valid when made, but is satisfied to modify it in light of agreement between the parties and additional compliance works, including stormwater drainage and remedial actions for bushfire safety. The modified development control order and remedial works address Council concerns and legal requirements, justifying both the amended demolition/retention orders and directing the issue of a Building Information Certificate upon compliance.
Court Disposition
Appeal upheld (both proceedings); development control order modified; Building Information Certificate to be issued upon compliance
Orders
- ['The appeal is upheld.' 'The development control order issued on 25 November 2019 is modified as per Annexure A.' 'Specified works in the modified order to be completed within times agreed or as extended.' 'Liberty reserved to apply for extensions if works cannot be completed within specified time due to reasonable...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment