MULTIPLEX CONSTRUCTIONS (NSW) PTY LTD AND ANOR v DALEGROVE PTY LTD [1992] NSWCA 165
The appeal is struck out for want of prosecution due to significant default in preparation, but the order is not to be taken out until an appropriate period after 7 August 1992, given the respondent's communication regarding absence and request for adjournment.
- Parties
- Applicant: Multiplex Constructions (NSW) Pty Ltd; Respondent: Dalegrove Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 20 July 1992
- Procedural Posture
- Application to Strike Out Notice of Appeal / Court of Appeal Ruling on Strike Out Application
- Outcome
- appeal struck out for want of prosecution, with deferred execution until 28 August 1992
- Legal Topics
- Want of Prosecution, Appeal Processes, Strike Out Application
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Multiplex Constructions (NSW) Pty Ltd
Applicant
Dalegrove Pty Ltd
Respondent
Procedural Posture
Application to Strike Out Notice of Appeal / Court of Appeal Ruling on Strike Out Application
Legal Issues
- 1 Whether notice of appeal should be struck out for want of prosecution
Ratio Decidendi
The appeal is struck out for want of prosecution due to significant default in preparation, but the order is not to be taken out until an appropriate period after 7 August 1992, given the respondent's communication regarding absence and request for adjournment.
Court Disposition
appeal struck out for want of prosecution, with deferred execution until 28 August 1992
Orders
- Appeal struck out for want of prosecution
- Order conditional upon service of judgment on Dalegrove Pty Ltd prior to 7 August 1992
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment