Tim Barr Pty Ltd v Narui Gold Coast Pty Ltd [2010] NSWSC 1106
Interest on the Plaintiff's judgment is awarded from the time each relevant payment of expenditure was made, at the rate prescribed at the time of the judgment as per the rules for s 101, based on the court's discretion under s 100. No apportionment of costs is warranted; the Defendant is entitled to all costs due to issue interconnection and lack of discrete successful issues for the Plaintiffs. Set-off between judgment sums and costs is appropriate, and enforcement of the Plaintiff's judgment is stayed pending quantification of Defendant's costs and set-off.
- Jurisdiction
- Australia
- Judgment Date
- 24 September 2010
- Procedural Posture
- Civil Equity Consequential Orders / Post Trial; Final Orders Following Substantive Decisions
- Outcome
- Short minutes of orders to be provided; judgment for Defendant on most issues. Set-off and stay granted pending costs quantification. Defendant to have costs.
- Legal Topics
- ['interest on Judgments' 'costs Orders' 'set Off of Judgments' 'restitution for Improvements' 'lease Termination']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil Equity Consequential Orders / Post Trial; Final Orders Following Substantive Decisions
Legal Issues
- 1 ['From what date and at what rate should interest be calculated on the restitutionary judgment?' 'Whether costs should be apportioned in respect of distinct issues or follow the general rule?' 'Should the court order set-off and a stay regarding enforcement of judgments and costs between the parties?']
Ratio Decidendi
Interest on the Plaintiff's judgment is awarded from the time each relevant payment of expenditure was made, at the rate prescribed at the time of the judgment as per the rules for s 101, based on the court's discretion under s 100. No apportionment of costs is warranted; the Defendant is entitled to all costs due to issue interconnection and lack of discrete successful issues for the Plaintiffs. Set-off between judgment sums and costs is appropriate, and enforcement of the Plaintiff's judgment is stayed pending quantification of Defendant's costs and set-off.
Court Disposition
Short minutes of orders to be provided; judgment for Defendant on most issues. Set-off and stay granted pending costs quantification. Defendant to have costs.
Orders
- ['Declaration that Defendant validly terminated the lease and option on 3 May 2002.' 'Declaration that exercise of option by First Plaintiff was ineffective.' 'Extension/vacation of caveat orders as per draft orders.' 'Judgment for Cross Claimant against First Cross Defendant in sum of $86,261.15 plus interest to be...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment