Network Ten Pty Ltd v Seven Network (Operations) Ltd [2014] NSWSC 752

Network Ten Pty Ltd v Seven Network (Operations) Ltd [2014] NSWSC 752

The Ten Agreement remained on foot, but Ten was unsuccessful in establishing breach of contract; as Seven and Stephens were substantially successful, costs followed the event and were awarded in their favour.

Jurisdiction
Australia
Judgment Date
06 June 2014
Procedural Posture
Civil / Final Judgment
Outcome
Declare Ten Agreement to be on foot; proceedings otherwise dismissed; costs awarded to defendants
Legal Topics
['costs' 'final Orders']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Civil / Final Judgment

  1. 1 ['Whether the Ten Agreement remained on foot' 'Whether there was a breach of contract by the defendants' 'Appropriate orders as to costs']

Ratio Decidendi

The Ten Agreement remained on foot, but Ten was unsuccessful in establishing breach of contract; as Seven and Stephens were substantially successful, costs followed the event and were awarded in their favour.

Court Disposition

Declare Ten Agreement to be on foot; proceedings otherwise dismissed; costs awarded to defendants

Orders

  • ['Declaration that the agreement made between the plaintiff and the second defendant on 6 March 2014 remains on foot' 'Proceedings otherwise dismissed' 'No order as to costs of 6 June 2014' "Plaintiff to pay the defendants' costs of the proceedings"]