Peninsula Balmain Pty. Limited v. Abigroup Contractors Pty. Limited [2002] NSWCA 211
The Court held there was no misleading or deceptive conduct or actionable breach of clause 23 by Peninsula in not disclosing the project management agreement, because the effect of the agreement did not inhibit the superintendent’s impartial certification role under the building contract; any non-disclosure was not shown to be non-inadvertent or to have a material misleading impact. Abigroup was entitled to extensions of time due to the superintendent’s ongoing power, even after termination, and was entitled to payment for specified variations and associated delay costs, subject to contractual limits. The referee erred in treating insurance coverage as a reason to automatically disallow...
- Jurisdiction
- Australia
- Judgment Date
- 03 July 2002
- Procedural Posture
- Appeal / Court of Appeal Judgment
- Outcome
- Appeal allowed. Orders below set aside. Matter remitted to referee for further determination on discrete issue. Respondent to pay appellant's costs.
- Legal Topics
- ['building Contracts' 'superintendent Role' 'variations and Extensions of Time' 'liquidated Damages' 'misleading or Deceptive Conduct']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Appeal / Court of Appeal Judgment
Legal Issues
- 1 ['Whether non-disclosure of project management agreement amounted to misleading or deceptive conduct under s.52 Trade Practices Act 1974 (Cth)' 'Whether non-disclosure was a breach of clause 23 of the contract' 'Entitlement to extensions of time and delay costs under the contract' 'Entitlement to variations and compliance with contract conditions' 'Entitlement for recovery of costs related to rectifying water damage']
Ratio Decidendi
The Court held there was no misleading or deceptive conduct or actionable breach of clause 23 by Peninsula in not disclosing the project management agreement, because the effect of the agreement did not inhibit the superintendent’s impartial certification role under the building contract; any non-disclosure was not shown to be non-inadvertent or to have a material misleading impact. Abigroup was entitled to extensions of time due to the superintendent’s ongoing power, even after termination, and was entitled to payment for specified variations and associated delay costs, subject to contractual limits. The referee erred in treating insurance coverage as a reason to automatically disallow...
Court Disposition
Appeal allowed. Orders below set aside. Matter remitted to referee for further determination on discrete issue. Respondent to pay appellant's costs.
Orders
- ['Appeal allowed.' 'Orders below set aside.' "Report of Mr. McDougall dated 19 February 2001, together with the supplementary report dated 27 February 2001, be adopted, subject to: (a) disallowance of variation VPR32; (b) Abigroup's delay costs to be calculated at $7,890.00 per day; (c) the referee's disallowance of...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment