Penn & Penn v The Fair Trading Administration Corporation [2000] NSWFTT 5
The Tribunal found, preferring the evidence of Professor Marosszeky and Mr Dickinson, that the defects were 'general defects' and not 'major structural defects' within the meaning of clause 31 of the BSC Regulations as they did not affect the structural integrity of the cavity brick walls. Furthermore, the Tribunal found that the delay in notification was not due to circumstances outside the Applicants' control, as a full building inspection was not obtained before purchase, which was a matter within their control. Accordingly, the Tribunal declined to exercise its discretion to extend the time for lodging the claim.
- Jurisdiction
- Australia
- Judgment Date
- 02 February 2000
- Procedural Posture
- Appeal / Decision
- Outcome
- Appeal dismissed
- Legal Topics
- ['home Building Defects' 'time Limits for Lodgement of Insurance Claims' 'definition of Major Structural Defect' 'tribunal Discretion on Extension of Time']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Appeal / Decision
Legal Issues
- 1 ["Whether the defects constitute 'major structural defects' under clause 31 of the BSC Regulations" 'Whether the Tribunal should exercise its discretion to accept the late claim under the BSC Comprehensive Insurance Scheme']
Ratio Decidendi
The Tribunal found, preferring the evidence of Professor Marosszeky and Mr Dickinson, that the defects were 'general defects' and not 'major structural defects' within the meaning of clause 31 of the BSC Regulations as they did not affect the structural integrity of the cavity brick walls. Furthermore, the Tribunal found that the delay in notification was not due to circumstances outside the Applicants' control, as a full building inspection was not obtained before purchase, which was a matter within their control. Accordingly, the Tribunal declined to exercise its discretion to extend the time for lodging the claim.
Court Disposition
Appeal dismissed
Orders
- ['The Tribunal confirms the decision of the Fair Trading Administration Corporation to refuse the claim by Mr & Ms Penn under the Building Services Corporation Comprehensive Insurance Scheme for losses in rectifying defective building work.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment