Pennings G & M v Wyong S C [2004] NSWLEC 160
The s 96 modification appeal was dismissed because the constructed works involved a significant increase in floor space and practical conversion of roof space into habitable areas that could be used as a separate dwelling, producing a considerably different and more intense development that was not substantially the same as the approved development. The modification also involved excessive encroachment into the coastal Hazard Zone without exceptional circumstances, increased risk in a major storm event, and did not reasonably comply with DCP 77 or the public interest. The Building Certificate appeal was adjourned because proposed removal and rectification works could bring the development...
- Jurisdiction
- Australia
- Judgment Date
- 06 April 2004
- Procedural Posture
- Appeals Against Refusal of a S 96 Modification and Refusal to Issue a Building Certificate / Ex Tempore Judgment After Concurrent Hearing
- Outcome
- The s 96 modification appeal was dismissed and the modification was refused; the Building Certificate appeal was adjourned for further details concerning removal of unauthorised works.
- Legal Topics
- ['section 96 Modification' 'substantially the Same Development' 'building Certificate' 'foreshore Erosion Zone' 'dual Occupancy']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Appeals Against Refusal of a S 96 Modification and Refusal to Issue a Building Certificate / Ex Tempore Judgment After Concurrent Hearing
Legal Issues
- 1 ['Whether the s 96 modification application related to substantially the same development as the approved development.' 'Whether the unauthorised works had acceptable merit having regard to coastal erosion impacts and DCP 77.' 'Whether the Building Certificate appeal should be determined or adjourned to allow further details, specifications and plans for rectification works.']
Ratio Decidendi
The s 96 modification appeal was dismissed because the constructed works involved a significant increase in floor space and practical conversion of roof space into habitable areas that could be used as a separate dwelling, producing a considerably different and more intense development that was not substantially the same as the approved development. The modification also involved excessive encroachment into the coastal Hazard Zone without exceptional circumstances, increased risk in a major storm event, and did not reasonably comply with DCP 77 or the public interest. The Building Certificate appeal was adjourned because proposed removal and rectification works could bring the development...
Court Disposition
The s 96 modification appeal was dismissed and the modification was refused; the Building Certificate appeal was adjourned for further details concerning removal of unauthorised works.
Orders
- ['The appeal is dismissed.' 'The s 96 modification to development application No. 1158/96 is refused.' 'The matter is adjourned to enable the parties to consider the extent of removal of the unauthorised work.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment