Anderson v Robert Stokes trading as the Minister of Planning and Public Spaces [2020] NSWLEC 138
Given the significant public interest in the Snowy Hydro 2.0 Project, its critical nature to energy security and the economy in NSW, and the serious prejudice and financial costs to SHL from delay, the Court grants expedition and fixes an early hearing date with appropriate procedural orders.
- Parties
- Applicant: Peter Anderson; First Respondent: Robert Gordon Stokes trading as The Minister of Planning and Public Spaces; Second Respondent: Department of Planning Industry and Environment; Third Respondent: Snowy Hydro Limited
- Jurisdiction
- Australia
- Judgment Date
- 18 September 2020
- Procedural Posture
- Judicial Review / Interlocutory Application for Expedition
- Outcome
- Expedition granted; hearing set for 10-12 November 2020 with procedural orders as outlined.
- Legal Topics
- Expedition of Hearing, Environmental Impact Assessment, Judicial Review
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Peter Anderson
Applicant
Robert Gordon Stokes trading as The Minister of Planning and Public Spaces
First Respondent
Department of Planning Industry and Environment
Second Respondent
Snowy Hydro Limited
Third Respondent
Procedural Posture
Judicial Review / Interlocutory Application for Expedition
Legal Issues
- 1 Whether expedition of the judicial review hearing should be granted
- 2 Whether the matter has special factors warranting early hearing
Ratio Decidendi
Given the significant public interest in the Snowy Hydro 2.0 Project, its critical nature to energy security and the economy in NSW, and the serious prejudice and financial costs to SHL from delay, the Court grants expedition and fixes an early hearing date with appropriate procedural orders.
Court Disposition
Expedition granted; hearing set for 10-12 November 2020 with procedural orders as outlined.
Orders
- The Applicant to serve an amended summons on or before 30 September 2020.
- If Respondents consent to leave to file amended summons, further procedural orders (Orders 4-11) apply.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment