Blake v Ku-ring-gai Council [2015] NSWLEC 1476

Blake v Ku-ring-gai Council [2015] NSWLEC 1476

Because an agreement under s 34(3) was reached and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were to be disposed of in accordance with that agreement without a merit assessment of the issues originally in dispute.

Jurisdiction
Australia
Judgment Date
24 November 2015
Procedural Posture
Class 1 Development Application / Conciliation Conference; Agreement Under S 34(3) of the Land and Environment Court Act 1979
Outcome
Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979.
Legal Topics
['development Application' 'multi Dwelling Housing' 'conciliation Conference' 'agreement Between the Parties Under S 34(3)']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 Development Application / Conciliation Conference; Agreement Under S 34(3) of the Land and Environment Court Act 1979

  1. 1 ['Whether an agreement under s 34(3) of the Land and Environment Court Act 1979 had been reached between the parties as to terms of a decision acceptable to them.' 'Whether the agreed decision was one that the Court could have made in the proper exercise of its functions.']

Ratio Decidendi

Because an agreement under s 34(3) was reached and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were to be disposed of in accordance with that agreement without a merit assessment of the issues originally in dispute.

Court Disposition

Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979.

Orders

  • ["Final orders to give effect to the parties' agreement were made on the date recorded on those orders."]