Monaghan v Holroyd City Council [2008] NSWLEC 1353

Monaghan v Holroyd City Council [2008] NSWLEC 1353

The Court found that the respondent's proposed orders largely achieved a balance between compliance with development consent and practical use of the land, adopting them with certain amendments sought by the applicant regarding driveway location and retention of access paving, as reflected on marked-up plans.

Jurisdiction
Australia
Judgment Date
29 August 2008
Procedural Posture
Appeal / Orders Following Hearing of Appeals Concerning Enforcement of Development Consent
Outcome
Orders made for partial removal of works, further landscaping, and various remedial actions as detailed in the orders for each property.
Legal Topics
['development Consent' 'non Compliance With Conditions' 'remedial Orders' 'landscaping' 'driveway Access']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal / Orders Following Hearing of Appeals Concerning Enforcement of Development Consent

  1. 1 ['Whether the applicant complied with conditions of the development consents for 192 and 194 Girraween Road' 'Appropriate remedial orders under s 121(B) following non-compliance' 'Appropriate works to remedy non-complying concrete, paving, and landscaping']

Ratio Decidendi

The Court found that the respondent's proposed orders largely achieved a balance between compliance with development consent and practical use of the land, adopting them with certain amendments sought by the applicant regarding driveway location and retention of access paving, as reflected on marked-up plans.

Court Disposition

Orders made for partial removal of works, further landscaping, and various remedial actions as detailed in the orders for each property.

Orders

  • ['For 194 Girraween Road, removal of excess concrete and creation of landscaped areas per marked-up plans within 8 weeks; additional landscaping works, compliance with specific development consent conditions including vehicular crossings, planting of specified trees, completion of remedial actions and required...