Batterham v Makeig [2010] NSWCA 86
On proper construction of clause 4 of the Kitchener Project Agreement, the fees imposed by the Council in November and December 2006, which were applied to consultants' costs in pursuit of development approval, were costs for which the respondent was liable. The respondent's refusal to pay those fees, viewed objectively, constituted a blanket refusal of an essential term and a repudiation of the contract, justifying the appellants terminating the agreement. There was no actionable misrepresentation as the appellants did not rely upon the respondent's representations about experience. As the respondent repudiated, his claims failed and the proceedings should be dismissed with costs.
- Parties
- First Appellant: Brian Joseph Batterham; Second Appellant: Batterham's Bus Lines Pty Limited; Respondent: Peter John Makeig
- Jurisdiction
- Australia
- Judgment Date
- 22 April 2010
- Procedural Posture
- Civil Appeal / Court of Appeal Determination on Appeal From Equity Division, Supreme Court of NSW
- Outcome
- Appeal allowed. Trial judgment and orders set aside. Proceedings and cross-claim dismissed with costs, orders for restitution and associated certificates as set out.
- Legal Topics
- Construction and Interpretation of Contracts, Repudiation of Contract, Quantum Meruit, Misrepresentation, Breach of Contract, Assessment of Damages, Misleading or Deceptive Conduct
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Brian Joseph Batterham
First Appellant
Batterham's Bus Lines Pty Limited
Second Appellant
Peter John Makeig
Respondent
Procedural Posture
Civil Appeal / Court of Appeal Determination on Appeal From Equity Division, Supreme Court of NSW
Legal Issues
- 1 Whether the Kitchener Project Agreement obliged the respondent to pay council fees that were being used to pay consultants' costs
- 2 Whether respondent breached or repudiated the Kitchener Project Agreement and whether this justified termination
- 3 Whether the representation that respondent was an experienced project consultant constituted misleading or deceptive conduct under the Fair Trading Act 1987 and if loss resulted
Ratio Decidendi
On proper construction of clause 4 of the Kitchener Project Agreement, the fees imposed by the Council in November and December 2006, which were applied to consultants' costs in pursuit of development approval, were costs for which the respondent was liable. The respondent's refusal to pay those fees, viewed objectively, constituted a blanket refusal of an essential term and a repudiation of the contract, justifying the appellants terminating the agreement. There was no actionable misrepresentation as the appellants did not rely upon the respondent's representations about experience. As the respondent repudiated, his claims failed and the proceedings should be dismissed with costs.
Court Disposition
Appeal allowed. Trial judgment and orders set aside. Proceedings and cross-claim dismissed with costs, orders for restitution and associated certificates as set out.
Orders
- Appeal allowed.
- Orders of Ward J set aside.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment