Agostino & Anor v Pittwater Council [2015] NSWLEC 1518

Agostino & Anor v Pittwater Council [2015] NSWLEC 1518

Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were required to be disposed of in accordance with that decision.

Jurisdiction
Australia
Judgment Date
10 December 2015
Procedural Posture
Class 1 Development Application Proceedings / Final Orders Following Conciliation Conference and Agreement Under S 34(3) of the Land and Environment Court Act 1979
Outcome
Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979; final orders were made on 10 December 2015.
Legal Topics
['development Application' 'conciliation Conference' 'agreement Between the Parties' 'orders Under S 34(3) of the Land and Environment Court Act 1979']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Class 1 Development Application Proceedings / Final Orders Following Conciliation Conference and Agreement Under S 34(3) of the Land and Environment Court Act 1979

  1. 1 ['Whether the agreement reached between the parties under s 34(3) of the Land and Environment Court Act 1979 was a decision the Court could have made in the proper exercise of its functions.' "Whether the proceedings should be disposed of in accordance with the parties' agreed decision."]

Ratio Decidendi

Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were required to be disposed of in accordance with that decision.

Court Disposition

Proceedings disposed of in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979; final orders were made on 10 December 2015.

Orders

  • ["Final orders to give effect to the parties' agreement were made on 10 December 2015."]