Pittwater Council v Martoriati (No 3) [2013] NSWLEC 214
The Court extended and varied the compliance dates because further expert work, survey information, design documentation, certification, and inspections were required before the respondent could complete the ordered remedial works, and because the temporary propping system could continue if inspected and maintained in accordance with the joint experts' requirements. The respondent was ordered to pay the Council's costs because his inability to comply with the existing orders necessitated the motion and there was no relevant conduct by the Council disentitling it to costs.
- Jurisdiction
- Australia
- Judgment Date
- 25 November 2013
- Procedural Posture
- Class 4 Civil Enforcement Proceedings / Respondent's Notice of Motion Filed 23 September 2013 to Vary Court Orders and Extend Time for Compliance; Consequential Orders
- Outcome
- Orders varied to extend time for compliance on specified terms; respondent ordered to pay the Council's costs of the motion as agreed or assessed.
- Legal Topics
- ['variation of Court Orders' 'extension of Time for Compliance' 'remedial Works to Land and House' 'geotechnical and Structural Certification' 'costs of Motion']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 4 Civil Enforcement Proceedings / Respondent's Notice of Motion Filed 23 September 2013 to Vary Court Orders and Extend Time for Compliance; Consequential Orders
Legal Issues
- 1 ['Whether the time for compliance with orders requiring final remedial works to the land and house should be extended.' 'Whether the design documents and certification for the remedial works to the land should be further prepared in accordance with agreed expert requirements.' 'Whether further time should be allowed for the respondent to consider whether to undertake final remedial works to the existing house or seek development consent to demolish and replace it.' "Whether the respondent should pay the Council's costs of the notice of motion."]
Ratio Decidendi
The Court extended and varied the compliance dates because further expert work, survey information, design documentation, certification, and inspections were required before the respondent could complete the ordered remedial works, and because the temporary propping system could continue if inspected and maintained in accordance with the joint experts' requirements. The respondent was ordered to pay the Council's costs because his inability to comply with the existing orders necessitated the motion and there was no relevant conduct by the Council disentitling it to costs.
Court Disposition
Orders varied to extend time for compliance on specified terms; respondent ordered to pay the Council's costs of the motion as agreed or assessed.
Orders
- ['The respondent must file and serve by 9 December 2013 a survey of the property prepared by a registered surveyor in accordance with paragraph 4(1) of the joint engineering experts report dated 15 November 2013.' 'Order 5 was varied so that the respondent must comply by 28 April 2014 instead of 29 November 2013.'...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment