Primelime (NSW) Pty Ltd v B.A.E.C. Contracting Pty Ltd [2018] NSWSC 372
Because the contract came to an end in January 2017 and did not provide for reference dates to survive termination, there was no statutory entitlement to make a payment claim for a reference date after termination. Therefore, the adjudicator lacked jurisdiction, and the determination must be quashed.
- Parties
- Plaintiff: Primelime (NSW) Pty Ltd; First Defendant: B.A.E.C. Contracting Pty Ltd; Second Defendant: Ted Smithies
- Jurisdiction
- Australia
- Judgment Date
- 22 March 2018
- Procedural Posture
- Equity Technology and Construction List / Judgment Ex Tempore
- Outcome
- Relief granted as sought in the summons; adjudication determination quashed; costs awarded to plaintiff; directions for draft orders.
- Legal Topics
- Security of Payment, Jurisdiction, Reference Date, Termination of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Primelime (NSW) Pty Ltd
Plaintiff
B.A.E.C. Contracting Pty Ltd
First Defendant
Ted Smithies
Second Defendant
Procedural Posture
Equity Technology and Construction List / Judgment Ex Tempore
Legal Issues
- 1 Whether adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (NSW) was valid
- 2 Whether a construction contract existed between the parties to the adjudication application
- 3 Whether the payment claim was made on or from a reference date
Ratio Decidendi
Because the contract came to an end in January 2017 and did not provide for reference dates to survive termination, there was no statutory entitlement to make a payment claim for a reference date after termination. Therefore, the adjudicator lacked jurisdiction, and the determination must be quashed.
Court Disposition
Relief granted as sought in the summons; adjudication determination quashed; costs awarded to plaintiff; directions for draft orders.
Orders
- Declaration in accordance with prayer 1 of the summons filed 24 October 2017
- Relief under s 69 of the Supreme Court Act 1970 (NSW) as sought in prayer 2
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment