Procorp Civil Pty Limited v Napoli Excavations and Contracting Pty Limited & Ors [2006] NSWSC 358

Procorp Civil Pty Limited v Napoli Excavations and Contracting Pty Limited & Ors [2006] NSWSC 358

Procorp failed to establish, on the evidence, that Napoli would be unable to repay the moneys if required. The purpose of the funds paid into Court was security for Procorp's challenge to the adjudication and judgment, and with Napoli having succeeded, the funds should now be paid out to Napoli. Final orders to pay out funds were appropriate, but execution/stay granted for a brief period to allow Procorp to approach the Court of Appeal.

Jurisdiction
Australia
Judgment Date
21 April 2006
Procedural Posture
Practice and Procedure Interlocutory Application / Final Orders—application to Pay Out Moneys Held in Court, Stay Pending Appeal
Outcome
Application to have funds paid out to Napoli granted; funds paid into Court to be paid to Napoli; orders stayed until midnight 1 May to allow Procorp to approach the Court of Appeal; receivers' application to have funds returned to them dismissed; existing injunction regarding $40,000 to remain in place pending...
Legal Topics
['security of Payment' 'interlocutory Relief' 'payment Out of Court' 'stay Pending Appeal']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Practice and Procedure Interlocutory Application / Final Orders—application to Pay Out Moneys Held in Court, Stay Pending Appeal

  1. 1 ['Whether moneys paid into Court as security should be paid out to Napoli Excavations and Contracting Pty Limited pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW)' 'Whether Procorp established that Napoli would not be able to repay the moneys if Procorp succeeded on final determination' 'Fate of $40,000 held by receivers pending security for costs application']

Ratio Decidendi

Procorp failed to establish, on the evidence, that Napoli would be unable to repay the moneys if required. The purpose of the funds paid into Court was security for Procorp's challenge to the adjudication and judgment, and with Napoli having succeeded, the funds should now be paid out to Napoli. Final orders to pay out funds were appropriate, but execution/stay granted for a brief period to allow Procorp to approach the Court of Appeal.

Court Disposition

Application to have funds paid out to Napoli granted; funds paid into Court to be paid to Napoli; orders stayed until midnight 1 May to allow Procorp to approach the Court of Appeal; receivers' application to have funds returned to them dismissed; existing injunction regarding $40,000 to remain in place pending...

Orders

  • ['Funds paid into Court ($202,254.36) to be paid out to Napoli Excavations and Contracting Pty Limited.' 'Orders stayed until midnight Monday, 1 May (to permit approach to Court of Appeal).' "Receivers' application for immediate payment of funds to them dismissed." 'Existing injunction/injunctive regime regarding...