Programmed Maintenance Services Limited, in the matter of Programmed Maintenance Services Limited [2017] FCA 1265
The scheme was agreed to by the requisite statutory majorities with full disclosure, there was no opposition or objection, an independent expert concluded the scheme was fair and reasonable, ASIC issued a no objection letter, and all statutory and procedural requirements were satisfied. Therefore, the scheme was approved and an exemption from s 411(11) was granted.
- Parties
- Plaintiff: Programmed Maintenance Services Limited
- Jurisdiction
- Australia
- Judgment Date
- 27 October 2017
- Procedural Posture
- Corporations Scheme of Arrangement / Approval Hearing (second Court Hearing)
- Outcome
- Scheme of arrangement approved; exemption from s 411(11) granted.
- Legal Topics
- Scheme of Arrangement, Court Approval of Scheme, Disclosure Requirements, Members' Meeting, ASIC Regulation, Takeover Regulation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Programmed Maintenance Services Limited
Plaintiff
Procedural Posture
Corporations Scheme of Arrangement / Approval Hearing (second Court Hearing)
Legal Issues
- 1 Whether to approve the scheme of arrangement under s 411(4)(b) of the Corporations Act 2001 (Cth)
- 2 Whether the scheme is fair and reasonable to members
- 3 Whether all procedural and statutory requirements are met, including disclosure and notice
Ratio Decidendi
The scheme was agreed to by the requisite statutory majorities with full disclosure, there was no opposition or objection, an independent expert concluded the scheme was fair and reasonable, ASIC issued a no objection letter, and all statutory and procedural requirements were satisfied. Therefore, the scheme was approved and an exemption from s 411(11) was granted.
Court Disposition
Scheme of arrangement approved; exemption from s 411(11) granted.
Orders
- Pursuant to s 411(4)(b) of the Corporations Act 2001 (Cth) the scheme of arrangement between the Plaintiff and its members, as set out in Annexure 'CGS-28' to the supplementary affidavit of Christopher Glen Sutherland sworn 28 August 2017, is approved.
- Pursuant to s 411(12) of the Act, the plaintiff be exempted from compliance with s 411(11) of the Act in relation to the scheme of arrangement referred to in order 1.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment