Residents Against Intermodal Development Moorebank Incorporated v Minister for Planning [2018] NSWLEC 1130
Consent was granted as conditions were found to adequately mitigate or offset the development's ecological, acoustic, traffic, air quality, contamination, and water impacts. The evidence before the Court demonstrated that impacts could be managed and that the proposal was in the public interest. The remaining areas of disagreement were addressed by imposing specific and updated conditions as set out in Annexure 'A', reflecting expert and lay evidence, ensuring ongoing monitoring and adaptive responses to impacts.
- Parties
- Applicant: Residents Against Intermodal Development Moorebank Incorporated; First Respondent: Minister for Planning; Second Respondent: Qube Holdings Limited
- Jurisdiction
- Australia
- Judgment Date
- 06 March 2018
- Procedural Posture
- Objector Appeal Under S98 Environmental Planning and Assessment Act 1979 (nsw) / Final Decision and Orders
- Outcome
- Appeal upheld; development consent granted
- Legal Topics
- Development Consent, Biodiversity Impacts, Noise and Acoustic Impacts, Traffic and Air Quality, Site Contamination, Water Quality, Endangered Species and Ecological Communities
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Residents Against Intermodal Development Moorebank Incorporated
Applicant
Minister for Planning
First Respondent
Qube Holdings Limited
Second Respondent
Procedural Posture
Objector Appeal Under S98 Environmental Planning and Assessment Act 1979 (nsw) / Final Decision and Orders
Legal Issues
- 1 Whether the development consent for the construction of an intermodal facility and rail link should be upheld given impacts on biodiversity, noise, traffic, air quality, contamination, water quality, and suitability of site.
- 2 Whether the conditions of consent adequately mitigate identified impacts, particularly for threatened species and affected residents.
Ratio Decidendi
Consent was granted as conditions were found to adequately mitigate or offset the development's ecological, acoustic, traffic, air quality, contamination, and water impacts. The evidence before the Court demonstrated that impacts could be managed and that the proposal was in the public interest. The remaining areas of disagreement were addressed by imposing specific and updated conditions as set out in Annexure 'A', reflecting expert and lay evidence, ensuring ongoing monitoring and adaptive responses to impacts.
Court Disposition
Appeal upheld; development consent granted
Orders
- The appeal is upheld.
- Development consent for the construction of an intermodal facility and rail link is granted in accordance with the application SSD 6766, subject to the final conditions in Annexure 'A'.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment