Lester v Minister for Planning [2011] NSWLEC 178
Given the nexus between the Aboriginal Heritage Impact Permit and Modification 7, and because the injunction could be limited to restrain salvage works solely for construction of new surface gas wells, the balance of convenience favoured granting a limited interlocutory injunction until the expedited final hearing; the applicant's delay did not disentitle him to that short, limited relief.
- Jurisdiction
- Australia
- Judgment Date
- 12 October 2011
- Procedural Posture
- Class 4 Proceedings / Interlocutory Application for Injunction Pending Expedited Final Hearing
- Outcome
- Interlocutory undertaking noted and limited interlocutory injunction granted until 4pm on 1 November 2011; costs reserved.
- Legal Topics
- ['development Consent Modification' 'aboriginal Heritage Impact Permit' 'interlocutory Injunction' 'balance of Convenience' 'delay']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 4 Proceedings / Interlocutory Application for Injunction Pending Expedited Final Hearing
Legal Issues
- 1 ['Whether an interlocutory injunction should restrain salvage work under the Aboriginal Heritage Impact Permit for the purpose of construction of new surface gas wells in reliance on Modification No 7 pending the final hearing.' "Whether the applicant's delay in commencing proceedings and pressing for interlocutory relief should disentitle the applicant to interlocutory injunctive relief." 'Whether the balance of convenience favoured a limited interlocutory injunction.']
Ratio Decidendi
Given the nexus between the Aboriginal Heritage Impact Permit and Modification 7, and because the injunction could be limited to restrain salvage works solely for construction of new surface gas wells, the balance of convenience favoured granting a limited interlocutory injunction until the expedited final hearing; the applicant's delay did not disentitle him to that short, limited relief.
Court Disposition
Interlocutory undertaking noted and limited interlocutory injunction granted until 4pm on 1 November 2011; costs reserved.
Orders
- ['The Court notes the undertaking of the second respondent to the Court in paragraph 1 of the short minutes of orders dated 12 October 2011.' 'Directions in accordance with paragraphs 2 to 8 of those short minutes.' 'Order that the second respondent be restrained from carrying out salvage works under the Aboriginal...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment