Shaw v Niru Construction Pty Ltd & Anor [2021] NSWDC 589

Shaw v Niru Construction Pty Ltd & Anor [2021] NSWDC 589

The defendants' application for adjournment was refused as the evidence did not establish that the intended witness (Mr Chaloub) was incapable of participating; case management, dictates of justice, delay considerations and materiality of the proposed evidence all weighed against granting adjournment.

Jurisdiction
Australia
Judgment Date
29 October 2021
Procedural Posture
Civil / Interlocutory Application (adjournment) at Final Day of Hearing
Outcome
adjournment application refused
Legal Topics
['adjournment' 'evidence' 'case Management']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Civil / Interlocutory Application (adjournment) at Final Day of Hearing

  1. 1 ["Whether the defendants' application for adjournment should be granted to allow a further witness (Mr Chaloub) to be called" 'Whether the medical evidence justifies the adjournment' 'Case management and dictates of justice under Civil Procedure Act 2005 (NSW)']

Ratio Decidendi

The defendants' application for adjournment was refused as the evidence did not establish that the intended witness (Mr Chaloub) was incapable of participating; case management, dictates of justice, delay considerations and materiality of the proposed evidence all weighed against granting adjournment.

Court Disposition

adjournment application refused

Orders

  • ['Application for adjournment by defendants refused.']