Ronghai Property Group Pty Limited v Ku-ring-gai Council [2017] NSWLEC 1070

Ronghai Property Group Pty Limited v Ku-ring-gai Council [2017] NSWLEC 1070

As the parties reached agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied the Court could have so ordered, the proceedings were disposed of in accordance with the agreement, with development consent granted and costs ordered accordingly.

Source-derived case information.

Jurisdiction
Australia
Judgment Date
16 February 2017
Procedural Posture
Development Application Appeal / Conciliation Conference—final Orders After Agreement
Outcome
Appeal upheld. Development consent granted. Orders by consent.
Legal Topics
['development Application' 'conciliation Conference' 'agreement Under S 34(3) Land and Environment Court Act 1979']
['planning and Environment Law'] ['development Application' 'conciliation Conference' 'agreement Under S 34(3) Land and Environment Court Act 1979']

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Development Application Appeal / Conciliation Conference—final Orders After Agreement

  1. 1 ['Whether agreement on development application can be effected by order under s 34(3) of Land and Environment Court Act 1979']

Ratio Decidendi

As the parties reached agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied the Court could have so ordered, the proceedings were disposed of in accordance with the agreement, with development consent granted and costs ordered accordingly.

Court Disposition

Appeal upheld. Development consent granted. Orders by consent.

Orders

  • ['Leave granted to the Applicant to rely on specified amended plans and documents.' "Applicant to pay the Respondent's costs agreed at $4,500.00 upon execution of this Agreement." 'The appeal be upheld.' "Development Consent granted to DA0350/16 for demolition of existing structures and construction of 9 townhouses...