Keogh v Samchris Pty Ltd [2024] NSWCATCD 32
The Tribunal found major defects existed and the respondent was liable, rejecting the s.18F defence and the design defect defence because the builder did not construct strictly in accordance with the option B drawings, and the drawings were prepared at the builder’s request, not on homeowner instructions. The preferred remedy was a work order for rectification of specified defects, as per s.48MA. The applicants' claim for a refund of variations was dismissed because no clear cause of action was pleaded and the claim was also out of time under s.48K(3), as all works were supplied by May 2019 and proceedings were commenced more than 3 years later.
- Parties
- First Applicant: Steven John Keogh; Second Applicant: Jacqueline Mary Keogh; Respondent: Samchris Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 08 March 2024
- Procedural Posture
- Home Building Dispute / Final Determination
- Outcome
- Orders for rectification made in respect of major defects; application otherwise dismissed; costs in the cause unless further application.
- Legal Topics
- Statutory Warranties, Major Defects, Rectification Orders, Building Contract Variations, Limitation Periods
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Steven John Keogh
First Applicant
Jacqueline Mary Keogh
Second Applicant
Samchris Pty Ltd
Respondent
Procedural Posture
Home Building Dispute / Final Determination
Legal Issues
- 1 Existence and extent of major and minor defects under the Home Building Act 1989 (NSW)
- 2 Whether the respondent can rely on a s.18F defence or design defect defence
- 3 Appropriate scope of rectification works
Ratio Decidendi
The Tribunal found major defects existed and the respondent was liable, rejecting the s.18F defence and the design defect defence because the builder did not construct strictly in accordance with the option B drawings, and the drawings were prepared at the builder’s request, not on homeowner instructions. The preferred remedy was a work order for rectification of specified defects, as per s.48MA. The applicants' claim for a refund of variations was dismissed because no clear cause of action was pleaded and the claim was also out of time under s.48K(3), as all works were supplied by May 2019 and proceedings were commenced more than 3 years later.
Court Disposition
Orders for rectification made in respect of major defects; application otherwise dismissed; costs in the cause unless further application.
Orders
- The respondent must, within six months, rectify Items 1–3, 28, 31, 73 (master bedroom water leak) in accordance with the agreed scope of work plus additional work as set out at CB1755–1757.
- The respondent must, within six months, rectify Items 4, 5–15, 16–18, 27, 33–68 in accordance with the agreed scope of works at CB1757–1762.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment