Sangain Pty Limited v Italform Pty Limited [2009] NSWSC 74
It was open to the Referee to find that Sangain relied on Italform's pre-contractual representations, notwithstanding the contract's delivery terms; Italform's challenge to the Referee's report for not addressing a new argument could not be entertained as it was not argued before the Referee; there was no error in the Referee's assessment of damages or consideration of mitigation; thus, the Referee's report should be adopted and judgment given for Sangain.
- Jurisdiction
- Australia
- Judgment Date
- 12 February 2009
- Procedural Posture
- Application for Adoption of Referee's Report / Judgment on Adoption of Referee's Report
- Outcome
- Referee's report adopted; judgment for Sangain in the sum of $1,929,204 exclusive of GST.
- Legal Topics
- ['misleading and Deceptive Conduct' 'breach of Contract' "adoption of Referee's Report"]
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Application for Adoption of Referee's Report / Judgment on Adoption of Referee's Report
Legal Issues
- 1 ['Whether the Referee erred in finding misleading and deceptive conduct' "Whether Sangain relied on Italform's representations inconsistent with the subsequent contract" 'Whether Italform could criticise the report for not addressing an argument not advanced at the reference' "Whether damages should be assessed as per the Referee's findings and whether mitigation was properly considered"]
Ratio Decidendi
It was open to the Referee to find that Sangain relied on Italform's pre-contractual representations, notwithstanding the contract's delivery terms; Italform's challenge to the Referee's report for not addressing a new argument could not be entertained as it was not argued before the Referee; there was no error in the Referee's assessment of damages or consideration of mitigation; thus, the Referee's report should be adopted and judgment given for Sangain.
Court Disposition
Referee's report adopted; judgment for Sangain in the sum of $1,929,204 exclusive of GST.
Orders
- ['Report adopted' 'Judgment for Sangain in the amount of $1,929,204 exclusive of GST' 'Further arguments to be heard on disposition of crane parts and costs']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment