Save Wallum Incorporated v Clarence Property Corporation Limited [2024] FCA 967

Save Wallum Incorporated v Clarence Property Corporation Limited [2024] FCA 967

Because the respondents accepted there was an arguable case for final relief, the decisive question was the balance of convenience. The Court was satisfied that construction of the Wallum Froglet breeding ponds posed a sufficient risk of irreparable harm to the Wallum Sedge Frog, particularly through sedge mining and the risk that ponds might not be maintained if permanent relief were granted, while the evidence did not establish substantial additional delay or prejudice to the respondents. The balance of convenience therefore favoured restraining pond construction and erosion and sediment control works, but permitted lower-risk or beneficial works including exclusion bunting on existing...

Jurisdiction
Australia
Judgment Date
23 August 2024
Procedural Posture
Application for an Interim Injunction Under S 475(5) of the Environment Protection and Biodiversity Act 1999 (cth) / Interlocutory Application Pending Determination of the Applicant's Application for a Permanent Injunction
Outcome
Interim injunction to be ordered with some exclusions; parties directed to provide draft agreed or competing orders to give effect to the judgment, with the existing interim injunction remaining in force in the meantime.
Legal Topics
['interim Injunction' 'environment Protection and Biodiversity Act 1999 (cth)' 'threatened Species' 'balance of Convenience' 'development Works' 'wallum Sedge Frog']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Application for an Interim Injunction Under S 475(5) of the Environment Protection and Biodiversity Act 1999 (cth) / Interlocutory Application Pending Determination of the Applicant's Application for a Permanent Injunction

  1. 1 ["Whether the applicant had an arguable case for a permanent injunction restraining the respondents' development works under the EPBC Act." 'Whether the balance of convenience favoured a wider interim injunction restraining additional ecological works pending determination of the permanent injunction application.' 'Whether alleged protest conduct by members of the applicant disentitled the applicant to interim injunctive relief.' 'Whether delay by the applicant in bringing the application should weigh against interim relief.' 'Whether particular proposed works, including Wallum Froglet breeding ponds, exclusion bunting, erosion and sediment controls, shallow ripping, hollows or nest boxes, and weed maintenance, should be permitted pending final determination.']

Ratio Decidendi

Because the respondents accepted there was an arguable case for final relief, the decisive question was the balance of convenience. The Court was satisfied that construction of the Wallum Froglet breeding ponds posed a sufficient risk of irreparable harm to the Wallum Sedge Frog, particularly through sedge mining and the risk that ponds might not be maintained if permanent relief were granted, while the evidence did not establish substantial additional delay or prejudice to the respondents. The balance of convenience therefore favoured restraining pond construction and erosion and sediment control works, but permitted lower-risk or beneficial works including exclusion bunting on existing...

Court Disposition

Interim injunction to be ordered with some exclusions; parties directed to provide draft agreed or competing orders to give effect to the judgment, with the existing interim injunction remaining in force in the meantime.

Orders

  • ['The parties provide draft agreed or competing orders to give effect to this judgment to the Associate of Justice Bromwich within 7 days.']