Zhou v Georges River Council [2016] NSWLEC 1277

Zhou v Georges River Council [2016] NSWLEC 1277

An agreement reached under s 34(3) of the Land and Environment Court Act 1979 was acceptable to the parties and satisfied the requirements for Court approval, requiring the Court to dispose of the proceedings in accordance with the agreement.

Parties
Applicant: Steve Zhou; Respondent: Georges River Council
Jurisdiction
Australia
Judgment Date
29 June 2016
Procedural Posture
Appeal / Conciliation Conference; Final Orders
Outcome
Appeal upheld; Development Consent granted for DA2015/0236 in accordance with Annexure A.
Legal Topics
Deletion of Deferred Commencement Conditions, Conciliation Conference, Agreement Between Parties, Orders

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 1
Sign in to unlock

Parties

Steve Zhou

Applicant

Georges River Council

Respondent

Procedural Posture

Appeal / Conciliation Conference; Final Orders

  1. 1 Whether to delete deferred commencement conditions following agreement at conciliation conference

Ratio Decidendi

An agreement reached under s 34(3) of the Land and Environment Court Act 1979 was acceptable to the parties and satisfied the requirements for Court approval, requiring the Court to dispose of the proceedings in accordance with the agreement.

Court Disposition

Appeal upheld; Development Consent granted for DA2015/0236 in accordance with Annexure A.

Orders

  • The appeal is upheld.
  • Development Consent is granted for Development Application No. DA2015/0236 in accordance with 'Annexure A'.